Case Study: Efficient School Building Demolition in Windsor with Feltham Demolition’s Grab-Hire Service

October 9, 2024by Feltham Demolition0

Project Overview

Feltham Demolition was tasked with handling the demolition of an old building at a secondary school in Windsor. The project was part of a redevelopment plan to construct a new, modern classroom block. The client, the school’s management, needed the site to be cleared immediately after the demolition to allow for the construction work to begin without delay.

The key challenge was ensuring the demolition and site clearance did not disrupt the ongoing school activities. With students and staff still present on campus, safety was a top priority, and the team needed to work within strict timeframes to minimise any interference with daily operations. Traditional skip-hire was impractical because multiple skips placed on the limited school grounds would have disrupted access routes and created safety concerns for students.

What We Did

We recommended our grab hire service as the best solution for site clearance. The grab hire option, which uses a grab lorry equipped with a hydraulic arm, allowed for fast and efficient waste removal with minimal disruption to the school environment. Unlike skips, which require time to fill and multiple placements, grab hire services can collect large volumes of waste in a single trip, reducing the need for constant on-site handling.

Once the grab hire lorry collected the demolition waste, it was transported back to Feltham Demolition’s yard for recycling. The team ensured that all materials—such as concrete, metal, and wood—were sorted and prepared for reuse in other construction projects.

Grab hire for school building demolition in Windsor
 

The Results

The school management was extremely pleased with the results of Feltham Demolition’s grab hire service. The site was cleared quickly and efficiently, allowing construction to begin on schedule. The entire operation took place without disrupting the school’s day-to-day activities, ensuring student safety and minimising inconvenience to the staff.

By choosing grab hire over skip-hire, the school saved both time and money, and they appreciated Feltham Demolition’s focus on recycling the materials from the project. This not only reduced costs but also aligned with the school’s environmental goals, helping them maintain a sustainable approach to the redevelopment.

Feltham Demolition and the Environment

Feltham Demolition is committed to promoting environmentally friendly practices by recycling materials from all demolition projects. After the school building was demolished, the collected waste was taken back to Feltham Demolition’s yard, where it was carefully sorted for recycling.

  • Concrete:
    The concrete from the demolished building was crushed and reused as aggregate in other construction projects. This recycled concrete could be used in Windsor for new infrastructure projects, such as the foundation of new buildings or roadworks, helping to reduce the need for newly quarried materials.
  • Metal:
    Metal materials, such as steel frames and pipes, were separated and sent to local recycling plants. Recycled metals are valuable in the construction industry and can be repurposed for use in the framework of new buildings or in manufacturing. For example, the steel from this project might be reused in Windsor’s growing number of commercial developments.
  • Wood:
    Any salvageable wood from the site was cleaned and prepared for reuse. Recycled timber is often used in refurbishment projects or as structural components in new builds. This wood could be repurposed in smaller construction projects across Windsor, promoting more sustainable building practices.

By recycling these materials, we helped reduce the amount of waste sent to landfills, contributing to a more sustainable construction industry in Windsor. This approach not only benefits the environment but also helps reduce costs for future building projects that use recycled materials.

For fast, efficient, and eco-friendly site clearance, Feltham Demolition’s grab lorry service is the perfect solution. Whether you’re working on a school, a commercial site, or any other project, our grab hire service can save you time, money, and ensure responsible recycling. 

Contact us today to learn more about how our grab hire services can benefit your next project.

Leave a Reply

Your email address will not be published. Required fields are marked *

Contact us now to get quote

About Feltham Demolition

Operating as a customer-focused demolition company, we undertake a range of services to meet your needs. From asbestos surveys to building strip outs and site clearance, we provide everything you need for safe and efficient projects.
https://feltham-demolition.co.uk/wp-content/uploads/2022/01/FD.png

Call Center

1-800-555-500

and get a free estimate

Newsletter Sign Up







    Call Now Button